Posted
[Ed. note: The following is an unedited press release. -J]
Cedar Point announced today that the opening of Maverick, the park’s 17th roller coaster, will be delayed until early June to make modifications to the coaster’s steel track.
The Media Preview of Maverick scheduled for Thursday, May 10 has been cancelled. The ride will not be in operation on Opening Day.
The decision to delay the opening of Maverick was based on pre-opening tests and consultation with IntaRide, the manufacturer of the ride. Based on these discussions, it has been determined that three sections of steel track following the launch tunnel should be replaced.
“We apologize to all of our guests for this inconvenience,” said John Hildebrandt, vice president and general manager of Cedar Point. “This decision was made in the interest of improving the guest experience on the ride and to eliminate excessive stress on the trains.”
The modification process is already underway and the park hopes to open the ride by early June.
~Rob Willi
So, Two weeks to make the track, two weeks at least shipping and then what? two weeks testing?
Chuck
My bet? They'll be back.
-'Playa
*** This post was edited by CoastaPlaya 5/8/2007 1:56:24 PM ***
Seriously... why does Cedar Fair keep giving this company business... or any amusement park owner/operator, for that matter? Wicked Twister needed structural work on the spikes and TTD was/is a disaster. I would think those two projects would have been enough to convince CF that they should be giving work to companies not named Intamin, but they did anyway with this one. Why is there any reason to believe this will be the last project handed to Intamin? No one- both Intamin and the companies that buy their rides- don't seem to learn from their mistakes.
My guess is the banking and or radius of curvature is too shallow, thus causing excessive g-forces. Still, I'm surprised they were off far enough on their calculations to warrant replacing track.
How does this happen with something so (allegedly) precisely engineered?
Jeff - Weren't you the one that told me CP doesn't make mistakes because they've built a ton of coasters and know what they're doing? Even if you do all the planning and design up front, people are bound to miss something or make a mistake. It's what happens in design and construction. They had a late addition of the catwalk over at the end of the ride too. What happened there? Why didn't they design and fabricate that whole structure in the factory? Because they overlooked something in the design.
You must be logged in to post